General Information

Tentative Completion Date October 31, 2018 (Tentative)
Project Manager Jeff Koza, Capital Projects Manager, 847-664-4124
Contractor A Lamp Concrete Contractors
Awarded Contract Amount Water Main Portion: $1,051,091
Asphalt Street Portion: $1,360,000
Funding Sources Bonds

Special Note - Receive E-mail Updates About This Project

The Village recognizes that this project will impact a large number of residents as well as parents and students at Wescott School. For that reason, the NotifyMe e-mail listserv is availlable to anyone who is interested in the project can get regular updates on the project as well as information on any detours. If you are interested, please subscribe at this link. Work is anticipated to begin in April and updates will begin shortly thereafter.



Project Description


This project will focus on the replacement of the original 1953 water main along Western Avenue from Techny Road and Maple Avenue. Once this work has been completed, crews will entirely reconstruct Western Avenue from Techny Road to Oak Avenue with asphalt (instead of the original concrete) and install new concrete curb and gutter. Work is expected to begin in April. 

Enabling Resolution:

A full description of the project can be found as part of Resolution 2018-20, which awarded the project to the Village's contractor.

Open House Documents from Tuesday, March 20:

On Tuesday, March 20, a special public meeting was held at Wescott School. Public Works staff was on hand to explain the project and answer questions. Copies of the meeting exhibits and documents are provided below. If you have any questions do not hesitate to contact the project manager.

Construction Notification Letters:

On Tuesday, March 20, Village staff hand delivered construction notices to all residents with homes that are located within the project limits (immediately adjacent to or located on Western Avenue). Residents with homes that require a new water service and shut off box received information about the potential impacts of the planned work. See the initial construction notice and frequently asked questions (FAQ) sheet.

​Wescott School Pick Up/Drop Off Traffic Plan

Beginning on or about Monday, April 2, construction work will restrict Western Avenue to one southbound traffic lane from Maple Avenue to Techny Road for the duration of the project. Parents picking up or dropping off their children at Wescott School will not be allowed to stand/park their vehicle on Western Avenue. Parents will be asked to queue on Farnsworth Lane. A project representative will be stationed at this intersection and will direct the next vehicle in line to proceed on to Western Avenue towards the school when space in the drop off lane opens up. A map showing the Wescott School pick up and drop off traffic control plan is provided at this link.

Project Contacts


The project contact for this project is Jeff Koza, Capital Projects Manager. Mr. Koza may be reached at 847-664-4124.

Current Project Update


April 20, 2018


This week, the Village’s contractor installed new water main along Western Avenue and completed the section between Brentwood Road and Farnsworth Lane. Next week, the contractor will continue installing main, moving north along Western. Additionally, crews will begin placing new fire hydrants and continue main installation at the intersections of Western and the various side streets.


Previous Project Updates


April 13, 2018

This week, the Village’s contractor installed approximately 1,200 feet of new water main along Western Avenue, between Bellevue Place and Brentwood Road. Next week, the contractor will continue placing new main moving north along Western. 



April 6, 2018

This week, the Village’s contractor installed a new connection to the existing water system at Techny Road and Western Avenue and began placing new water main along Western between Techny and Bellevue Place. 


March 30, 2018 - Western Avenue Lane Closures Begin Monday, April 2

This week, the Village’s contractor completed utility markings and saw cutting to prepare for the removal of the old water main. Crews will begin full construction on Western Avenue on Monday morning, April 2. Beginning April 2, Western Avenue will be closed to through traffic with one southbound lane open to local traffic between Walters Avenue and Techny Road. Initial work will include the installation of new water main beginning at Techny Road and heading north. As part of this initial work, crews will be completing a temporary water shut down for customers located near the intersection of Techny and Western on Monday, April 2, from 9 a.m. to 5 p.m. All impacted customers have been notified.


March 21, 2018 - Work to begin week of Monday, March 26

On Wednesday, March 21, Village staff met with the project contractor, School District 30, Northbrook Park District, the Northbrook Police Department and Northbrook Fire Department at the project preconstruction meeting. At this time, staff anticipates that the contractor will begin water main installation work on or around Monday, April 2. The contractor plans to begin at Techny Road and work northward on Western Avenue. Residents and those traveling to Wescott School should expect preparatory work to begin the week of Monday, March 26. This work will include completing utility locates, construction surveying/staking, limited material deliveries, pavement saw cutting and construction detour/warning sign installation.


March 16, 2016 - Contract Awarded

On Tuesday, March 13, the Village Board approved Resolution 2018-10, awarding this project to A Lamp Concrete Contractors of Schaumburg. Details of the contract can be found at this link.



March 1, 2018 - Open House Details

A special public meeting will be held at Wescott School on Tuesday, March 20, 2018 from 5:30 to 7:00 p.m. for residents and parents who would like to learn more about the project. See the invitational flyer and more details on the open house at this link

Work is expected to begin in April.


December 27, 2017 - Work Announcement

Work on this project is anticipated to begin in spring 2018. Future updates will be posted here as they become available.