General Information

Tentative Completion Date August 31, 2018 (Tentative)
Project Manager Martin Sobanski, Project Manager, 847-664-4118
Contractor Glenbrook Excavating & Concrete
Awarded Contract Amount $783,790
Funding Sources Bonds

Project Description


This project will focus on the replacement of the original 1960's water main along Bordeaux Drive (from Bordeaux Court to Brittany Road), Normandy Lane (from Dauphine Avenue to its east end) and the 600 block of Dauphine Avenue.

Enabling Resolution:

A full description of the project can be found as part of Resolution 2018-26, which awarded the project to the Village's contractor.


Project Contacts


For questions regarding this project, please contact Martin Sobanski, Project Manager. Mr. Sobanski can be reached at 847-664-4118 or via the GONorthbrook system

Current Project Update


January 12, 2018 - Work Announcement

Work on this project is anticipated to begin in late spring 2018. Future updates will be posted here as they become available.