Willow Creek Subdivision Projects 2022

Completion Date November 30, 2022
Project Manager Aram Beladi, 847-664-4133
Contractor Lenny Hoffman Excavating, Inc.
Awarded Contract Amount $2,258,188 (Water Main and Stormwater)
Funding Sources Bond Proceeds

Special Note - Receive E-mail Updates About This Project

The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is available to anyone who is interested in the project can get regular updates on the projects.  If you are interested, please subscribe at this link. Updates will begin when the project commences in summer 2021.

Project Description:

The Willow Creek projects will be completed in two phases. The first phase will include water main improvements including the replacement of the original 1960's main on Longmeadow Drive, Elm Ridge Drive and Kingston Drive. Following completion of that work, asphalt roadway resurfacing will be completed on those same roadways. Phase two work will be completed in 2022 on the portions of Canterbury, Woodland and Wood located within the Willow Creek subdivision.

Enabling Resolutions

On Tuesday, March 8, 2022, the Village Board approved Resolution 2022-21, which awarded the contract for Water Main and Storm water improvements to Lenny Hoffman Excavating, Inc. of Wilmette, Illinois.

Project Communications:



On Wednesday, February 23 2022, the Village mailed the construction notice for 2022 work. Please see a copy of this notice at this link.
  1. Additionally, the Willow Creek Storyboard has been updated to further detail 2022 construction work. 

    Finally, a Landscaping Impact Exhibit has been developed to show grading, clearing, and expected tree removal locations as a result of the stormwater improvement project. 

Project Contacts

For questions regarding this project, please contact Aram Beladi, Project Manager. Mr. Beladi can be reached at 847-664-4133 or via the GONorthbrook system

Current Project Update



Friday, May 13

This week, the contractor continued installing new water main on Canterbury Drive between Wood Drive and Elm Ridge Drive. The contractor continued work in the drainage ditch and began dredging of the ditch.  Final surface installation took place on streets started in 2021. 

Next week the contractor intends to continue installing new water main on Canterbury Drive between Wood Drive and Elm Ridge Drive and continue work in the drainage ditch.

Friday, May 6


This week, the contractor continued installing new water main on Wood Drive between Canterbury Drive and Woodland Drive.  Additionally, the contractor completed tree removal in the drainage ditch and began ditch work.   Structures were adjusted in areas impacted by 2021 construction in preparation for final resurfacing.

Next week, the contractor will begin installing new water main on Canterbury Drive between Wood Drive and Elm Ridge Drive.  The contractor intends to continue work in the drainage ditch and begin dredging of the ditch.   Final surface installation will take place on streets started in 2021.

Friday, April 29


This week, the contractor installed new water main on Wood Drive between Canterbury Drive and Woodland Drive as well as new hydrants on Woodland Drive.  Additionally, the contractor continued fence and tree removal for the rear yard drainage ditch between Canterbury Drive and Woodland Drive.   Areas of construction from 2021 started roadway milling and resurfacing. 

Next week, the contractor intends to continue installing new water main on Wood Drive between Canterbury Drive and Woodland Drive.  The contractor will also continue tree removal in the drainage ditch and begin dredging.   Areas impacted by 2021 construction are expected to be complete. 

Friday, April 22


This week, the contractor connected the newly installed water main to the existing main at Woodland Drive and Pfingsten Road.  Additionally, areas impacted by 2021 construction were restored with sod.  The contractor also began fence and tree removal for the rear yard drainage ditch between Canterbury Drive and Woodland Drive.

Next week the contractor intends to install new water main on Wood Drive between Canterbury Drive and Woodland Drive as well as install new hydrants.  The contractor also intends to continue fence and tree removal for the rear yard drainage ditch between Canterbury Drive and Woodland Drive.  The areas impacted by 2021 construction will begin roadway resurfacing.

Friday, April 15


This week, the contractor continued water main installation on Woodland Drive.  Additionally, areas impacted by 2021 construction were prepared for sod restoration. 

Next week, the contractor intends to connect the newly installed water main to the existing main at Woodland Drive and Pfingsten Road, as well as install new water main on Wood Drive between Canterbury Drive and Woodland Drive.  Finally, the contractor intends to begin fence and tree removal for the rear yard drainage ditch between Canterbury Drive and Woodland Drive.

Areas impacted by the 2021 construction will also make progress next week with final sod restoration and paving of the roadways.  Both sod restoration as well as resurfacing operations are weather dependent.

Friday, April 8
This week, the contractor began new water main installation on Woodland Drive between Wood Drive and Pfingsten Road.  Next week, the contractor intends to continue water main installation on Woodland Drive between Wood Drive and Elm Ridge Drive.  Additionally, sod restoration for areas impacted by 2021 construction will occur.

Friday, April 1


This week, the contractor began layout, mobilization, and asphalt preparation for the project.  Next week, the contractor intends to begin new water main installation on Woodland Drive between Wood Drive and Pfingsten Road.

Friday, March 25


Next week, the contractor intends to begin layout and asphalt removal in preparation for new water
main installation.  This work will occur on Woodland Drive and Wood Drive.   They will also begin mobilization of equipment and materials to the subdivision.

Thursday, November 24


This week, the contractor finished the asphalt driveway repairs, filling dirt behind the curbs,
removing equipment, and bringing the area to a safe condition for the winter.  The project is on hold for the winter; the contractor will finish the remaining resurfacing next year.


Thursday, November 18


This week, the contractor did brick driveway repairs and driveway patching on Longmeadow and Elm Ridge Dr.  Additional landscaping work will follow.

Thursday, November 11


This week, the Contractor completed base patching operations. Next week, the Contractor will fill-in the area behind the curbs near the north end of the project and finish all driveway restorations. 

Thursday, November 5


This week, the contractor completed all of the concrete work including curb, sidewalk, and concrete driveways on Kingston Dr., Elm Ridge Dr., Wood Dr., and Longmeadow Dr.  Next week, the contractor will work on asphalt base patching on these streets, followed by pavement removal for the rest of week.

Thursday, October 28


This week, the contractor poured concrete curb on portions of Kingston., Wood and Elm Ridge and began removing curb on the northern side of Longmeadow, Wood and Elm Ridge in preparation for additional curb replacement in those areas next week.



Thursday, October 21


This week, the contractor removed and began replacement of curb on Kingston, Wood and Elm Ridge.  The contractor will also install string line for the placement of longer curb sections using a curb machine. This string acts as a guide for the machine and allows the placement of curb without special forms. These longer sections of curb will be installed early next week, weather permitting.

Thursday, October 14

This week, the Contractor completed saw cutting of old curb on Longmeadow, Wood ad Elm Ridge. Next week, cut curbs will be removed in preparation for replacement and paving work.


Thursday, October 7


Next week, the Contractor is anticipated to begin curb removal and replacement work on Longmeadow Drive, Wood Drive and Elm Ridge Drive.  


 
Thursday, September 30

This week, the Village's contractor began staking work in anticipation of curb replacement beginning next week on Longmeadow, Elm Ridge and Wood. 

Thursday, September 16


At this time, staff anticipates curb and resurfacing work will begin in the next few weeks. Details will be posted once they become available.


Thursday, September 9

Next week, staff anticipates that the Village’s asphalt resurfacing contractor will begin resurfacing and curb work on Longmeadow, Elm Ridge and Kingston. Regular updates will be posted as more details become available Initial work will include any curb work before the surface of the roadways are milled for resurfacing. 



Thursday, September 2

The contractor has completed all water main work associated with this phase of the project. Asphalt street resurfacing work will begin in the near future.

Friday, August 27

The contractor will perform temporary parkway and pavement restoration measures during the week of August 30.

Friday, August 20

The contractor will connect the new main to the existing main on Pfingsten and Kingston as well as well as perform the removal of old hydrants and valves during the week of August 23.

Friday, August 6

The contractor will begin pressure testing and chlorinating the new water main.  Once the new main is in service they will begin connecting residential water services to the new water main.

Friday, July 30

The contractor will continue installing new watermain in the roadway on Kingston and Elm Ridge. They will then begin pressure testing and chlorinating the new water main.

Friday, July 16

The contractor will continue installing new watermain in the roadway on Kingston and Elm Ridge. 

Friday, July 2

The contractor will continue temporary restoration work on Longmeadow and Elm Ridge.  They will then begin grinding the roadway on Kingston and Elm Ridge to prepare for installation of the new water main on those roadways. 

Friday, June 25

The contractor will make final water main connections at the intersections of Canterbury and Elm Ridge as well as Pfingsten and Longmeadow and begin temporary restoration work on Longmeadow and Elm Ridge.  They will then begin grinding the roadway on Kingston and Elm Ridge to prepare for installation of the new water main on those roadways. 

Friday, June 18

This week, the Village's contractor will connect existing water service lines to the new water main, generally starting on Longmeadow near Pfingsten and heading eastward toward Elm Ridge. Affected homes will experienced temporary water outages as their home is being transferred to the new main. Notices will be delivered to homes prior to work taking place on their service line.

Friday, June 11

This week, the Village's contractor pressure tested and chlorinated the new water main on Elm Ridge. Once this new main is in service, the contractor will begin connecting residential water services to it. 

Friday, June 4

The contractor is continuing to install new water main in the roadway on Elm Ridge.  They will then begin installing fire hydrants and pressure testing the new water main.

Friday, May 28

The contractor is continuing to install new watermain in the roadway on Longmeadow.  They will then install watermain in the roadway on Elm Ridge from Longmeadow to Canterbury. 


May 21, 2021


The contractor intends to begin new watermain installation in the roadway starting on Longmeadow near Pfingsten.  Roadway watermain installation will proceed eastward towards Elm Ridge Dr.