2023 - Northbrook Highlands and Park Subdivision Projects

Completion Date November 30, 2023
Project Manager Aram Beladi, 847-664-4133
Contractor Mauro Sewer Construction, Inc. (Water Main Improvements)
Awarded Contract Amount $2,999,898
Funding Sources Bond Proceeds

Special Note - Receive E-mail Updates About This Project

The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is available to anyone who is interested in the project can get regular updates on the projects. If you are interested, please subscribe at this link. Updates will begin when the project commences in spring 2023.
 

Project Description:

This project will focus on the replacement of the original 1950's main on Butternut Lane, Penfold Place, and Summerton Place.  Additionally, the original 1940’s main will be replaced on Ash Lane, Cedar Lane, and Peachtree Lane.  This project will occur in conjunction with the scheduled street rehabilitation projects along these roads.

Enabling Resolutions

On Tuesday, March 14, 2023, the Village Board approved Resolution 2023-29, which awarded the contract for Water Main and Storm water improvements to Mauro Sewer Construction, Inc. of Des Plaines, Illinois.

Project Communications:

On Tuesday March 7, 2023, the Village mailed the construction notices for this work.  Separate Construction Notices were provided to both subdivisions impacted by this project.  
 
The Construction Notice provided to the Northbrook Park Subdivision can be found at this link.
The Construction Notice provided to the Northbrook Highlands Subdivision can be found at this link. 

Project Contacts

For questions regarding this project, please contact Aram Beladi, Project Manager. Mr. Beladi can be reached at 847-664-4133 or via the GONorthbrook system

Current Project Update

Friday, June 2

This week, the contractor began transferring service lines from the old water main to the new water main.  Additionally, they continued bringing additional segments of the water main into service.  

Next week, the contractor intends to continue transferring service lines from the old water main to the new water main.  Additionally, they intend to continue bringing additional segments of the new water main into service. 

Friday, May 26

This week, the contractor continued water main installation on Peachtree Lane and Ash lane and began bringing segments of water main into service in preparation for transferring services to the new water main.

Next week, the contractor intends to complete the remaining water main installation by completing the Ash Lane water main south of Peachtree and installing remaining hydrants. Additionally, they intend to begin transitioning service lines from the old water main to the new water main. Notices will be provided to alert residents prior to the start of service work.

Friday, May 19

This week, the contractor continued water main installation on Peachtree Lane and Ash Lane.

Next week, the contractor intends to continue water main installation on Peachtree Lane and Ash lane and begin bringing segments of water main into service in preparation for transferring services to the new water main.

Friday, May 12

This week, the contractor continued work on Peachtree Lane and began water main installation on Ash Lane .

Next week, the contractor intends to continue water main installation on Peachtree Lane and Ash lane.

Friday, May 5

This week, the contractor continued new water main installation on Ash Lane and connected the new main to the existing main by Dundee Road.

Next week, the contractor intends to continue work on water main installation on Peachtree Lane moving south. Additionally, the new main on Cedar Lane will be pressure tested and chlorinated to begin to bring it into service.

Friday, April 28

This week, the contractor finished work on water main installation on Cedar Lane and began work on water main installation on Ash Lane.

Next week, the contractor intends to continue work on water main installation on Ash Lane, moving south. On Monday May 1, 2023 the contractor intends to perform a water main shut off. Notices were sent to affected residents.

Friday, April 21

This week, the contractor continued work on water main installation on Cedar Lane.

Next week, the contractor intends to continue work on water main installation on Cedar Lane, moving south.

Friday, April 14

This week, the contractor began work on water main installation at the intersection of Ash Lane and Cedar Lane by Dundee Road.

Next week, the contractor intends to continue work on water main installation on Cedar Lane, moving south.

Friday, April 7

This week, the contractor began work grinding the asphalt roadway in locations where the trench will be dug for the proposed water main. Additionally, the contractor began work on mobilization, site layout, and tree protection.

Next week, the contractor intends to continue grinding the asphalt roadway. Additionally, the contractor intends to begin water main installation.

Friday, March 31

Next week, the contractor intends to grind the asphalt roadway in locations where the trench will be dug for the proposed water main. Additionally, the contractor will mobilize equipment and materials.  Finally, the contractor intends to begin water main installation.

Friday, March 24

The contractor has informed the Village that they intend to begin work in the Highlands Subdivision (Ash, Cedar, and Peachtree), construction layout and staking is expected to occur next week.  Project Updates for the Northbrook Park subdivision (Butternut, Penfold, Summerton) are expected to begin in late April or early May.