2024 – Dundee Road Water Main Improvements
| Anticipated Start Date | March 2024 |
| Anticipated Completion Date | September 2024 |
| Project Manager | Joe Petykowski, jpetykowski@baxterwoodman.com, 847-894-0064 |
| Contractor | Bolder Contractors, Inc. |
| Awarded Contract Amount | $2,668,450 |
| Funding Sources | Bond Proceeds |
Special Note - Receive E-mail Updates About This Project
The Village recognizes that this project will impact a large number of residents living in the immediate area. For that reason, the NotifyMe e-mail listserv is available to anyone who is interested in receiving regular updates on the project. If you are interested, please subscribe at this link. Updates will begin when the project commences in spring 2024.
Project Description:
This project will focus on the replacement of critical transmission water main that was originally installed in the 1960's on Dundee Road between Western Avenue and Meadow Road. This main will be installed primarily using trenchless methods to cross the West Fork of the North Branch of the Chicago River as well as the Metra Rail Corridor. Connections will be made to existing water mains near the intersections of Dundee Road and Ash Lane, Fair Lane, and Meadow Road.
Enabling Resolution:
This project is expected to be considered during the January 23, 2024 Board of Trustees regular meeting. Resolutions will be provided here once they become available.
Project Communications:
On Friday, February 12, 2024, the Village mailed the construction notice for the Dundee Road Water Main Improvements Project. The construction notice can be viewed at this link.
On Friday, March 8, 2024, a flyer was posted on the village's website to notify residents about the upcoming construction. The flyer can be viewed at this link.
Project Contacts
For questions regarding this project, please contact Joe Petykowski, Project Manager with Baxter & Woodman Consulting Engineers at 847-894-0064 or via e-mail at jpetykowski@baxterwoodman.com. Additionally, questions may be directed to Aram Beladi, Assistant Village Engineer. Mr. Beladi can be reached at 847-664-4133 or via the GONorthbrook system.
Current Project Update
Friday, June 14
This week, the newly installed transmission main was brought into service. Additionally, the contractor completed landscaping areas impacted by the project, performed site cleanup, and de-mobilized. While minor punch list items remain, work on this project is substantially completed.
Friday, June 7
This week, the contractor chlorinated and flushed the newly installed water main. Water samples were taken from the newly installed watermain; if satisfactory results are returned, the main will be brought into service early next week.
Next week, the contractor intends to complete landscaping areas impacted by the project, cleanup the site, and de-mobilize.
Friday, May 31
This week, the contractor will continue bringing the newly installed water main into service, and continued site restoration.
Next week, the contractor intends to complete bringing the newly installed water main into service, and begin landscaping areas impacted by the project.
Friday, May 24
This week, the contractor continued bringing the newly installed water main into service. Additionally, they connected the new water main to the old water main at Fair Lane and Meadow Road and began site restoration.
Next week, the contractor will continue bringing the newly installed water main into service and continue site restoration.
Friday, May 17
This week, the contractor began bringing the newly installed water main into service. Additionally, the contractor began abandoning old infrastructure at Ash Lane and Dundee Road.
Next week, the contractor will continue to bring the newly installed water main into service. Additionally, they will connect the new water main to the old water main at Fair Lane and Meadow Road.
Friday, May 10
This week, the contractor began connecting the newly installed water main to the existing water main in the north parkway on Dundee Road. There was a daytime lane closure for westbound traffic while work was being performed in the north parkway.
Next week, the contractor will begin bringing the newly installed water main into service. Additionally, the contractor will begin abandoning the old infrastructure at Ash Lane and Dundee Road.
Friday, May 3
This week, the contractor connected the segment of main from under the railroad tracks to the intersection of Dundee Road and Meadow Road. Additionally, they began installing water main across Dundee Road near Meadow Road. The Meadow Road southbound closure was reopened to traffic.
Next week, the contractor intends to perform connections of the newly installed water mains to the existing water main in the north parkway on Dundee Road. There will be a daytime lane closure for westbound traffic while work is being performed in the north parkway.
Friday, April 26
This week, the contractor prepared for installation of new water main under Dundee Road from Meadow Road, and continued installation of water main towards Meadow Road from the railroad tracks.
Next week, the contractor will prepare for connecting the new water main to the old water main on the north side of Dundee Road. The northerly westbound lane of Dundee Road will be closed during working hours.
Friday, April 19
This week, the contractor completed installation of water main across Dundee Road near Ash Lane. Additionally, they completed installing water main connections at the intersection of Dundee Road and Fair Lane.
Next week, the contractor will connect the segment of main from under the railroad tracks to the intersection of Dundee Road and Meadow Road. Additionally, they will begin installing water main across Dundee Road near Meadow Road. Southbound traffic on Meadow Road near Dundee Road will be restricted for approximately two weeks while water main is installed at the intersection.
Friday, April 12
This week, the contractor began installing water main across Dundee Road near Ash Lane. Additionally, they began installing water main connections at the intersection of Dundee Road and Fair Lane.
Next week, the contractor will continue drilling operations on Ash Lane, as well as installing water main connections at Fair Lane.
Friday, April 5
This week, the contractor completed drilling operations to install the new water main between Fair Lane and Ash Lane. They installed the water main under the river by pulling the fused pipe through the drilled shaft on Thursday, April 4th. Additionally, they continued installation of the water main under the railroad.
Next week, the contractor will complete installation of new water main under the railroad tracks and will install water main connections at Fair Lane. Additionally, they will begin directionally drilling water main under Dundee Road near Ash Lane.
Friday, March 29
This week, the contractor continued drilling operations to install the water main between Fair Lane and Ash Lane. Additionally, they began trenchless installation of the new water main under the railroad tracks. During a recent visit this week to the construction site, it was determined that, due to the work area's proximity to the road, the lane closure cannot be removed at the end of each workday as initially planned. Safety is a top priority in all construction projects and we anticipate completing the phase of the project causing the full-time lane closure within the next couple of weeks. We will then transition to requiring only daytime closures until all the main pipe work is finished by the first week of May.
Next week, the contractor intends to complete drilling operations to install the new water main between Fair Lane and Ash Lane. They intend to install the water main under the river by pulling the fused pipe through the drilled shaft on Wednesday, April 3rd. Finally, they intend to begin installing the water main towards the intersection of Dundee Road and Meadow Road.
Friday, March 22
This week, the contractor began drilling operations to install the water main between Fair Lane and Ash Lane. Additionally, they excavated bore pits to begin installing water main under the railroad tracks between Meadow Lane and Ash lane.
Next week, the contractor intends to continue drilling operations to install the new water main between Fair Lane and Ash Lane. Additionally, they will begin the trenchless installation of the new water main under the railroad tracks between Meadow Lane and Ash lane.
Friday, March 15
This week, Ash road access to Dundee road was closed; additionally the contractor began mobilization, clearing, and excavation of drilling pits to prepare for drilling operations.
Next week, the contractor intends to begin drilling operations to install the new water main between Fair Lane and Ash Lane.
Friday, March 8
Next week, the contractor intends to continue mobilization of materials and equipment along Dundee Road. They will also begin excavating the drilling and receiving trenches required for the water main installation.
A closure of Ash Lane access to Dundee Road will begin on Monday, March 11. This closure is anticipated to last through May.